Site Flatwork & Paving in Colorado
For Property Managers, GCs & Boards

Commercial Site Flatwork & Paving

Lots, drive aisles, and walks built for delivery loads instead of passenger cars.

Scope

Everything In This Scope

Each line below is a scope we bid, schedule, and pour ourselves. Open one for specifications, sequencing, and the questions worth asking before award.

A parking lot never fails where the cars park. It fails at the trash enclosure, at the loading door, on the two turns the delivery truck makes every Tuesday, and down the drive aisle the fire lane runs along. Those spots carry the real axle load, and they decide what a property spends on paving over twenty years.

We build commercial flatwork across the Front Range: lots, access roads, loading aprons, sidewalks, and the tie-ins between them. Most of a scoping conversation is about load spectrum and access, not finish. Tell us the heaviest vehicle that visits on a schedule and how many hours a day the site has to keep trading, and most of the design falls out of those two answers.

Design to the heaviest recurring vehicle, not the average one

Passenger cars are close to irrelevant structurally. A loaded refuse truck lifting a container, or a tractor dropping trailer landing gear on a bare slab, applies more load through a few square inches than a parking bay sees in a year. So the section gets zoned. Thin where cars sit, thick where trucks turn, thickest at the pad the container lands on.

Joint layout follows the same logic. Sawcut on the day of the pour at spacing matched to the section, and keep joints out of the primary wheel path where geometry allows, because a joint under repeated forklift or steer-axle traffic is where spalling starts. At construction joints in truck areas we dowel, so adjacent panels deflect together instead of stepping apart. Reinforcement is #4 bar on chairs at roughly a 24 inch grid anywhere trucks run. Mesh is fine under cars, and fiber replaces neither.

Section by traffic zone

Starting points for takeoff purposes. Final section comes from the geotechnical report and the actual vehicle mix on site.
ZoneTypical thicknessReinforcementJoint spacing
Car parking bays4 inchesWelded wire mesh held at mid-slabRoughly 8 to 10 feet
Drive aisles and fire lanes6 inches#4 bar on chairs, 24 inch gridRoughly 12 to 15 feet
Refuse enclosure and approach8 inches, thickened edges#4 bar, tighter gridPanel sized to the pad
Loading apron and dock front8 inches, dowelled joints#4 bar plus dowels at cold jointsSized to the truck path
Sidewalks and connectors4 inchesMesh or fiber for light dutyMatched to walk width

The sub-base and the water are the whole job

Concrete pavement is only as good as what it sits on. We proof-roll the subgrade before base goes down, because a soft spot found under a loaded tire costs a morning and the same spot found after the pour costs a panel. Aggregate base goes in compacted lifts, thicker under the heavy zones. On expansive clay, which is most of this metro, the answer is sometimes moisture conditioning, sometimes removal and replacement, sometimes separation fabric over soft subgrade. The geotech report tells us which.

Then drainage, where lots go wrong quietly. Every square foot has to shed to an inlet. We want positive fall everywhere rather than a flat plane that ponds at the joints and works freeze and thaw into them all winter.

Accessibility complicates that. Accessible routes and stalls cap cross slope at 1:48, ramp runs at 1:12, with 36 inch clear width, 60 inch landings, and detectable warnings at curb ramps. Drainage wants slope and accessibility limits it, so the grading plan solves both at once instead of picking a winner.

1:48maximum cross slope on an accessible route
1:12maximum running slope on a ramp run
36"minimum clear width, accessible route
7 daysbefore a new phase reopens to cars
Send us the site plan and the vehicle list

We'll return a zoned section, a phasing sequence, and unit pricing you can hold a subcontractor to. Estimates are free. Call (303) 569-4046.

Concrete against asphalt on a twenty year view

Neither one wins everywhere. The right answer usually splits the site by what drives over each part of it.
ConcreteAsphalt
Day one cost per square footHigherLower
Time to reopen7 days for cars, 28 to full design strengthHours
Recurring maintenanceJoint sealant, occasional panel swapSeal coat on a cycle, crack fill, eventual overlay
Under static trailer legsHolds. Point load spreads through the slabDeforms, and worse in summer heat
Repair unitOne panel, sawcut joint to jointA patch, whose edge becomes the next crack
Where it usually winsDumpster pads, dock aprons, drive aisles, turning truck trafficLarge low-traffic parking fields where first cost decides

Phasing a lot that has to keep operating

The number that governs a phasing plan is seven days, because that's how long a new pour waits before cars roll on it. Not one day, not a weekend. So a phase is offline about a week, and the sequence gets drawn around stall counts, the accessible route to each entrance, and a fire lane that stays open throughout. Confirm that last one with the authority having jurisdiction before the schedule locks.

We normally break a lot into quarters or thirds, sawcutting the phase boundary on a panel line and dowelling the cold joint so the next phase ties in structurally rather than butting against it.

Night and weekend placements come up constantly on retail and medical sites. Weekends usually beat nights. A night pour in shoulder season means heated water, non-chloride accelerator, blankets, and finishers under temporary light. All of it doable, all of it more expensive. And we won't place on frozen ground at any hour.

What we want in the bid package

  • Geotechnical report, or written permission to price against an assumed subgrade
  • Vehicle mix, including the heaviest unit that visits on a regular schedule
  • Hours the property must stay open and any noise restrictions in effect
  • Inlet, utility, and light pole base locations, and who owns adjustment of each
  • Whether existing section is removed full depth or overlaid
  • Accessible route from stalls to each entrance, and who is certifying it
  • Line items you want priced as adds and deducts by the unit

Coordination is most of the schedule risk

Concrete rarely sits alone in a site package. Striping follows us and needs clean, dry, cured surface, so that subcontractor's window is set by our pour dates rather than the other way around. Anything cast in gets confirmed before placement: light pole bases, bollard sleeves, EV conduit, irrigation sleeves under drive aisles. Coring a finished 8 inch slab to fix a missed sleeve is an expensive lesson.

Traffic control is scope, not an afterthought. Signage, cones, flaggers where trucks cross a live aisle, and a marked pedestrian route that stays accessible while the permanent one is closed. Then barricade the fresh pour harder than seems necessary. Somebody always drives on it.

The phasing plan gets written twice. Once on paper, and once the first morning, when we find out where the delivery drivers actually go instead of where the site plan says they go.

Site superintendent, commercial flatwork
Site Flatwork & Paving

Questions from property managers and general contractors

Still unsure about something?

Call the crew at (303) 569-4046 and we will talk it through.

Plan on about a week per phase. Demolition and base work take a day or two, the pour is one day, then seven days before cars return and 28 to full design strength. A higher early-strength mix can compress that window, and we'll price it as an alternate.

Sometimes, and we're careful about recommending it. A bonded or unbonded overlay needs a stable base underneath, and asphalt that's already rutting under trailer legs is not stable. We'd rather remove full depth in the heavy zones and overlay only where the existing section proves out under a proof-roll.

For anything carrying truck traffic, yes. Without one we're guessing at subgrade strength, and the guess has to be conservative, which means you pay for section you may not need. A report usually saves more than it costs on a lot of any size. Pavement design assumptions get confirmed against it.

We can carry it or you can hold it separately. Either way the sequencing is ours to protect: paint goes on cured, clean, dry concrete, so striping is scheduled off our pour dates. Layout gets approved before anyone paints, because restriping a lot twice is a change order nobody enjoys.

It can, and that determination isn't ours to make unilaterally. Scope, cost, and what counts as an alteration all factor in. We'll flag every non-conforming slope, stall, and curb ramp inside the work area in writing, and you confirm the requirement with your building department before we set grades.

With unit prices established in the original bid: square yard of removal, square foot by thickness, linear foot of curb, each for inlet adjustment. Quantities move on site work, they always do, so the protection is agreeing on the rate up front rather than mid-phase.
Where We Work

Site Flatwork Across The Front Range

Keep Looking

Other Commercial Work

Finished concrete project at a Colorado home

Bidding Site Flatwork This Season?

Send drawings or a site address and we will walk it, mark the scope, and return a written per-unit breakdown.